Valencia SWCD / GRGWA Monitoring Reports
10-Yr Post-Treatment Monitoring:

Valencia SWCD Belen 1, 2, 3, 4 Sites 10-yr Post-Treatment monitoring report
This report covers pre-treatment and 5 and 10-year-post-treatment vegetation monitoring assessments
performed on non-native phreatophyte removal projects near Belen, NM submitted by the Valencia Soil
and Water Conservation District to the Greater Rio Grande Watershed Alliance in 2011.

Valencia SWCD Project Tome 11.09, 10-yr Post-Treatment Report, 2022
This report covers pre-treatment and 5 and 10-year-post-treatment vegetation monitoring assessments
performed on non-native phreatophyte removal projects near Belen, NM submitted by the Valencia Soil
and Water Conservation District to the Greater Rio Grande Watershed Alliance in 2011.

Belen-1-2-3-4-Sites, 10-yr Post-Treatment Monitoring Report, 2023, Valencia SWCD
Belen-1-2-3-4-Sites, 10-yr Post-Treatment Monitoring Report, 2023, Valencia SWCD

Willie Chavez Park South – Belen 11.07, 10-yr Post-Treatment Report
This report covers pre-treatment and 5 and 10-year-post-treatment vegetation monitoring assessments
performed on non-native phreatophyte removal projects near Belen, NM submitted by the Valencia Soil
and Water Conservation District to the Greater Rio Grande Watershed Alliance in 2011. Following a
discussion of the ecological context, and our monitoring methods, we present pertinent background,
observations, and assessment results for each project.
5-Yr Post-Treatment Monitoring:

Pino Fire Restoration Project 14.16, 5-yr Post-Treatment Report, 2021, GRGWA
Pino Fire Restoration Project 14.16, 5-yr Post-Treatment Report, 2021, GRGWA, Valencia SWCD

16.18 Rio Abajo North, 5-yr Post-Treatment Monitoring Report, 2021, GRGWA, Valencia SWCD
Rio Abajo North 16.18, 5-yr Post-Treatment Report, 2021, GRGWA, Valencia SWCD

Valencia SWCD Belen 1, 2, 3, 4 Sites, 5-year Post-Treatment Monitoring Report
Belen 1-5 projects,5-year Post-Treatment Monitoring Report, 2016. Valencia SWCD

Valencia SWCD Los Lunas Bridge – Belen, 5-year Post-Treatment Monitoring Report, 2016
Valencia SWCD Los Lunas Bridge – Belen, 5-year Post-Treatment Monitoring Report, 2016

Valencia SWCD Willie Chavez Park South – Belen, 5-year Post-Treatment Monitoring Report, 2016
Valencia SWCD Willie Chavez Park South – Belen, 5-year Post-Treatment Monitoring Report, 2016
5-Yr Photo Comparisons:

5-year Photo Comparisons for Willie Chavez, 2 plots
5-year Photo Comparisons for Willie Chavez, 2 plots Valencia SWCD
Pre-Treatment Monitoring:

Willie Chavez Park South – Belen, Valencia SWCD, Pre-Treatment Monitoring, 2012
Willie Chavez Park South – Belen, Valencia SWCD, Pre-Treatment Monitoring, 2012

Pino Fire Restoration Project 14-16, Pre-treatment Monitoring Report, 2015
Pino Fire Restoration Project 14-16, Pre-treatment Monitoring Report, 2015

Los Lunas Bridge, Pre-Treatment Monitoring Valencia SWCD, 2012
Los Lunas Bridge- Belen, Pre-Treatment Monitoring Valencia SWCD, 2012

Rio Abajo North Riparian Treatment Project 16-18, Pre-treatment Report, 2016
Rio Abajo North Riparian Treatment Project 16-18, Pre-treatment Monitoring Report, 2016. Valencia SWCD.

Rio Abajo Project 15-16, Valencia SWCD 2015, Pre-Treatment Report, 2015
Rio Abajo Project 15-16, Valencia SWCD 2015. Pre-treatment Monitoring Report
Partner Reports:

2012 Horizon Environmental Services Final Report
2012 Horizon Environmental Services Final Report, Includes reports for projects on East Rio Arriba SWCD (Alcalde North), Santa Fe – Pojoaque SWCD (5 projects), and Valencia SWCD (Belen 1-5)